What is an IPMR?

What is an IPMR?

The Integrated Program Management Report (IPMR) is a contractually required report, prepared by the contractor, containing performance information derived from the contractor’s internal Earned Value Management System (EVMS). It provides the status of progress on the contract. [ 1]

What is the main purpose of the Integrated Program Management report IPMR Format 6?

The purpose of the IPMR is to provide early identification of problems that may have significant cost, schedule and/or technical impacts, and report the effects of management actions and project status information for use in making and validating management decisions.

What is Ipmdar?

The IPMDAR contains data for measuring contract execution progress on Department of Defense (DoD) acquisition contracts. The IPMDAR’s primary purpose to the Government is to reflect current contract performance status and the forecast of future contract performance.

What is the main purpose of the IPMR format 4?

Format 4 provides staffing forecasts. Format 5 is a narrative report used to provide the required explanations of changes and analysis of data contained in Formats 1-4 and 6.

What is the main purpose of the IPMR format 1 shown here?

The purpose of the IPMR is to help the Government understand a contractor’s cost and schedule performance by communicating a program’s cost and scheduling information between the prime contractor and the Government. The report is used to: Integrating cost, schedule, and technical performance data.

What are some of the types of information the IPMR format 3 provides?

Integrating cost, schedule, and technical performance data. Identifying potential problem areas that may cause significant cost variance and schedule variance. Providing valid, timely, and accurate contract status information.

What is the importance of the IPMR format 5?

Format 5 is a narrative report used to provide the required explanations of changes and analysis of data contained in Formats 1-4 and 6. Format 6 defines and contains the contractor’s Integrated Master Schedule (IMS). Format 7 defines the time-phased historical & forecast cost submission.

Who is responsible for Statusing the integrated master schedule?

In an Integrated Program Management (IPM) environment, the Master Scheduler (sometimes called a Program Master Scheduler or Integrated Master Scheduler) is an experienced scheduler who is responsible for maintaining the Integrated Master Schedule (IMS) for one or more programs.

What is an example of the type of things control account managers?

Control account managers use information from several software tools to assist in managing the control account. These might include the scheduling engine, the cost engine or EVM reporting tool. Some examples include: Deltek wInsight.

How often must the contractor submit Integrated Program Management report IPMR formats 1 6?

Monthly
Monthly Submission Requirement. The IPMR Formats 1-6 shall be required at least monthly. The reporting frequency shall be identified in the CDRL.