approximately four weeks
The process of obtaining the results of the analysis will take around seven days from the sample being taken, and then, a report will be drawn up. Generally, the Phase II ESA will take approximately four weeks.

What is a limited Phase II ESA?

A Phase II ESA is a limited subsurface investigation that is performed when you have reason to believe there may be contamination on the site and need to establish how likely it is that contamination occurs. Typically, this means there was a Recognized Environmental Condition (REC) discovered during the Phase I ESA.

What is the purpose of a Phase II ESA?

The purpose of a Phase II Environmental Site Assessment Report is to evaluate the presence, or absence of, petroleum products or hazardous substances in the subsurface of the site.

When did Phase I ESA start?

November 1, 2006
The EPA’s All Appropriate Inquiries Rule governing the scope of Phase I Environmental Site Assessments went into effect on November 1, 2006, and provided specific scope requirements for a Phase I ESA to meet the requirements of CERCLA’s innocent landowner defense.

How much does a Phase 2 environmental Assessment cost?

The Phase II Environmental Site Assessment cost is typically between $5,000 and $8,500 (for a standard commercial lot). Sometimes, Phase 2 ESAs can cost as much as $25,000. Clients seeking the price of a Phase II Environmental Site Assessment usually attract themselves towards the lowest cost Phase II ESA proposal.

How much does a Phase 2 Environmental Assessment cost?

How much does a Phase II cost?

The price of a Phase II Environmental Site Assessment can vary, depending on the aspects of a property. The Phase II Environmental Site Assessment cost is typically between $5,000 and $8,500 (for a standard commercial lot). Sometimes, Phase 2 ESAs can cost as much as $25,000.

Why get a Phase I ESA?

A Phase I ESA identifies recognized environmental conditions (RECs) that could impact the value of a specific property. With these assessments, you will know whether the site has had any problems with chemical or hazardous materials in the past.

What is a Phase 2 report?

A Phase 2 Environmental Site Assessment or a Phase II Environmental report is a scientific test whereby geologists drill and sample soil, soil-vapor, and groundwater to test for pollution.

What is a Phase III ESA?

A Phase III Environmental Site Assessment (ESA), also known as a remedial investigation or feasibility study, is yet another crucial step in environmental due diligence when conducting a property transaction or when developing a property that requires remedial action.

How much does a Phase 2 Esa cost?

Sometimes, Phase 2 ESAs can cost as much as $25,000. Clients seeking the price of a Phase II Environmental Site Assessment usually attract themselves towards the lowest cost Phase II ESA proposal.

How much does a Phase II Environmental Site Assessment cost?

The price of a Phase II Environmental Site Assessment can vary, depending on the aspects of a property. The Phase II Environmental Site Assessment cost is typically between $5,000 and $8,500 (for a standard commercial lot). Sometimes, Phase 2 ESAs can cost as much as $25,000.

What should a Phase II ESA report include?

A Phase II ESA report should describe the investigative activities completed, detailing soil borings performed, environmental phase II and the soil and ground water analytical results as compared to applicable state standards. Conclusions are then drawn from the data collected.

What is O Reg 153/04 for Phase II ESA’s?

the Ontario Regulation (O. Reg.) 153/04 for Phase II ESA’s, and ASTM International, ASTM E1903-11 We provide Phase 2 Environmental Site Assessment services to: Commercial, Industrial, Real Estate, Agriculture, Mining, throughout Toronto, the Greater Toronto Area and Ontario.